1998 - 2009

 

October 23, 1998 – Merrifield begins term at NRC

 

November 2006 – NRC Chair taps Merrifield to lead Combined License Review Task Force

 

March 1, 2007 Westinghouse/Shaw Consortium completes framework agreement that includes early funding with China’s State Nuclear Power Technology Company to build four AP1000 nuclear power plants in China

 

April 17, 2007 – With a 4-1 vote, the NRC approved the final rule on “Limited Work Authorizations,” which one power plant lobbying firm says responds “favorably to industry comments” and “eliminates a major impediment” for new power plant construction. In addition to voting in support of the rule, Merrifield had championed the rule to ease environmental and oversight restrictions for construction activities at nuclear power plants. Few companies stood to benefit more from this “Limited Work Authorizations” rule than the Shaw Group.

 

April 18, 2007 – Task Force published the “Report of the Combined License Review Task Force,” which was distributed to the Commissioners for review

 

May 23, 2007 – Merrifield signs, on behalf of the NRC, the Memorandum of Cooperation on Nuclear Safety for the Westinghouse Advanced Pressurized Reactor (AP1000) with the National Nuclear Safety Administration of the People’s Republic of China. Shaw has a 20% ownership position in Westinghouse

 

June 8, 2007 – Merrifield accepted an offer to serve as Senior Vice President of Shaw Power Group

 

June 14, 2007 – Merrifield visits with General Electric inAlbany,New York, regarding job search. General Electric picks up the ~$800 travel tab.

 

June 21, 2007 – Merrifield prepares his final SF 278 Executive Branch Personnel Public Financial Disclosure reports

 

June 22, 2007 – NRC approves the recommendations of the Combined License Review Task Force. Merrifield recuses himself from vote.  

 

June 26-30, 2007 – Merrifield and family accept visit to the Shaw Group in Baton Rouge, Louisiana. Shaw picks up the $2,915.87 tab.

 

June 30, 2007 – Merrifield’s term officially expires and he is not reappointed

 

July 3, 2007 – Merrifield signs SF 278 forms, without including job search trips

 

July 11, 2007 – Shaw Group Inc. announced that Merrifield would assume the position of Vice President of its Power Group

 

July 24, 2007 – The Shaw Group, along with Westinghouse Electric Company, signed multi-billion-dollar contracts to build four AP1000 nuclear power plants inChina

 

August 20, 2007 – Merrifield begins position of Senior Vice President of Shaw Power Group

 

September 14, 2007 – POGO writes NRC Chairman Klein with concerns about Merrifield’s transition from the government to go work for the Shaw Group, given his central involvement with a recent decision that benefitted the Shaw Group 

 

January 23, 2008 – Shaw Group announces its new office in Shanghai, China, “to support the rapidly growing Chinese nuclear power marketplace.”

 

April 28, 2009 – Shaw Group announces that it has signed a strategic cooperation agreement with China’s State Nuclear Power Technology Corporation

 

May 29, 2009 – POGO submits a FOIA to the NRC for documents related to investigations into Merrifield’s post-employment actions and negotiations

 

June 10, 2009 – NRC IG denies POGO’s FOIA on the grounds that release of documents would interfere with an enforcement proceeding. POGO contacted NRC’s enforcement division, and multiple sources said there were no enforcement actions being considered

 

July 8, 2009 – POGO appeals NRC’s denial of its May 29, 2009, FOIA but was again turned down

 

August 7, 2009 – POGO requests Merrifield’s SF 278 Executive Branch Personnel Public Financial Disclosure Reports from the NRC

 

August 24, 2009 – Merrifield sends two amended schedules to the SF 278 form he signed on July 3, 2007, that outline a trip he took to the Shaw Group and to General Electric

 

September 1, 2009 – NRC IG plans to conclude an investigation into Merrifield  