Recent Posts
-
DynCorp Accused of Being a Deadbeat
June 18, 2013 -
Does America Have a Security-Industrial Complex?
June 18, 2013 -
GAP Releases Statement on Snowden and the NSA
June 17, 2013 -
NSA Leak Prompts Talk of Limiting Contractor Access to Secrets
June 17, 2013 -
Government Errors Hurt Small Businesses
June 14, 2013 -
Final Inspector General’s Report Cuts References to Panetta’s Disclosure of “TOP SECRET” Info
June 14, 2013 -
When Will the Contractors Contract?
June 14, 2013 -
Cap Fight! Debate Continues Over Contractor Compensation
June 14, 2013 -
Lost? The Guards at Y-12 Can Help
June 13, 2013
SIGAR Slams Army Corps for Letting DynCorp Walk Off the Job
TweetOctober 26, 2012
On Thursday, the government’s Afghanistan reconstruction watchdog released a report showing that the U.S. military has failed to address serious construction deficiencies at an Afghan Army garrison that have persisted for more than two years. The report also criticized the military’s handling of the construction contractor, DynCorp International, which was released of its obligation to repair the deficiencies.
The U.S. Army Corps of Engineers (USACE) paid DynCorp almost $71 million to oversee construction of the garrison, Camp Pamir, in Kunduz Province on Afghanistan’s northern border. In April 2010, the Special Inspector General for Afghanistan Reconstruction (SIGAR) reported that the facilities at Camp Pamir were at risk of structural failure because of poor site grading and serious soil stability issues. During a follow-up inspection this year, SIGAR found that USACE had failed to address the soil stability problem, and identified additional structural failures (one of which is pictured above), improper grading, and new sink holes.
Perhaps the most troubling finding is that, despite DynCorp’s unsatisfactory performance, USACE released the contractor in December 2011 under a settlement that absolved DynCorp of responsibility for fixing the structural defects. Not only was DynCorp paid in full and released from all existing or future warranty obligations, USACE also retroactively extended the contract duration date by 948 days (to make it appear that DynCorp had met contractual deadlines) and changed DynCorp’s unsatisfactory performance ratings to satisfactory.
According to SIGAR, the settlement “appears to be on unfavorable terms to the U.S. government.”
“While the settlement closed out both contracts and relieved DynCorp of substantial current and future contractual liability for construction defects and other issues, USACE appears to have received little or nothing in return,” the report concluded.
Taxpayers took a nearly $2 million hit to pay for another company to come in and complete DynCorp’s work, and comprehensive remediation of the site will leave us on the hook for millions more.
SIGAR determined that the settlement with DynCorp violated a provision of the Federal Acquisition Regulation requiring contract settlements above a certain dollar amount to be submitted for independent agency review before they are finalized. SIGAR has asked USACE to provide a written explanation of its rationale behind the settlement.
POGO has written before about DynCorp’s checkered history in Afghanistan. The company currently ranks as the 32nd largest federal contractor in POGO’s Federal Contractor Misconduct Database, with more than $2 billion in contracts in fiscal year 2010. It is one of the prime contractors on the Army’s multi-billion dollar LOGCAP IV logistics support contract.
In recent years, some high-ranking government officials have gone through the revolving door to DynCorp. For example, former Commission on Wartime Contracting in Iraq and Afghanistan commissioner Michael Thibault last year became a vice president at DynCorp. There have even been a few Army revolvers: former CENTCOM Commander Anthony Zinni, Former Army Chief of Staff General Peter Schoomaker, and retired Generals John Tilelli and James Myles have recently held, or still hold, senior positions at DynCorp.
Image: Exterior Structural Failure, Building 603 (latrine), Kunduz Army Garrison, March 2012. Special Inspector General for Afghanistan Reconstruction (SIGAR), Kunduz ANA Garrison: Army Corps of Engineers Released DynCorp of all Contractual Obligations Despite Poor Performance and Structural Failures, SIGAR Inspection – 13-1, October 2012.
Neil Gordon is an investigator for the Project On Government Oversight. Neil investigates and maintains POGO's Federal Contractor Misconduct Database.
Topics: Contract Oversight
Related Content: Inspector General Oversight, SIGAR
Authors: Neil Gordon
Stay Connected
Browse POGOBlog by Topic
POGO on Facebook
Latest Podcast
Podcast: Family Matters
In March 2011, AllGov reported that DARPA, the Pentagon's premier research arm, had awarded a contract to a company founded by the agency's director. Wired's Spencer Ackerman joined POGO staffers to discuss how it all went down.