Page B from POGO's Report
Federal Contracting: Lessons Learned from Hurricane Katrina



Confusion about the Stafford Act

The Robert T. Stafford Disaster Relief and Emergency Assistance Act is the primary legislation governing FEMA’s response to catastrophic disasters, yet FEMA and other key federal entities have consistently struggled to enforce and understand the law (Attachment F).  During Hurricane Katrina, FEMA and other agencies were not prepared to implement the Stafford Act’s preference for the use of contractors already residing or doing business in the affected area.58 Unfortunately, this is not a new problem: a 1993 GAO report examining federal disaster management, especially the response to Hurricane Andrew, found that federal agencies failed to mobilize local resources and undertake advance preparations because they were unsure about what the statutory guidance required.59

In its examination of federal agency responses to Hurricane Katrina, the House Select Committee to Investigate the Preparation for and Response to Hurricane Katrina found that the Stafford Act’s ambiguous statutory guidance regarding local contractor participation resulted in few local firms receiving contracts and ongoing disputes over procuring contracts for debris removal and other services.60

Inadequate Competition

To better evaluate goods and services and get the lowest practical cost the government must encourage competition.61  Competition is essential to prevent waste, fraud, and abuse, and it promotes integrity in government spending.  Moreover, by opening federal contracting competition to all contractors (including small and minority businesses), the government will expand its opportunities beyond the currently closed club of federal contractors. No-bid or sole source contracts may be necessary in some cases and there are existing exceptions found in federal regulations, but they should be used sparingly.  During Katrina, the federal government missed awarding contracts to the best and brightest contractors, relying instead on the familiar and convenient.

Lack of competition and re-competing

By the end of September 2005, it was reported that 80 percent of dollars spent on contracts, approximately $1.5 billion, had been awarded without full and open competition.62  The government estimated that 58.8 percent of the Hurricane Katrina contracts awarded before November 30, 2005, were noncompetitive. The justification for allowing no-bid contracts was the urgent need for rapid emergency response. However, other government reports have found that 50.5 percent of the contracts have continued to be awarded noncompetitively – despite the fact that an emergency action is no longer required and, therefore, no longer justifies no-bid contracts.63

According to the June 30, 2006, President’s Council for Integrity and Efficiency (PCIE) Hurricane Katrina Report,64

Competitive awards were not used for the vast majority of large contracts, causing the government to buy goods and services at non-competitive prices.

The most glaring example of the negative impacts of non-competitive contracting was the four no-bid contract awarded to Fluor, CH2M Hill, Bechtel, and the Shaw Group.  Awarded after Katrina hit land, FEMA awarded each company a contract with a ceiling price of $500 million.  On October 6, 2005, FEMA Director Paulison testified before the Senate Homeland Security and Governmental Affairs Committee that he has “never been a fan of no-bid contracts” and that FEMA would “re-bid all of those no-bid contracts.”  Re-bidding did not occur, however, until August 2006. In fact, FEMA actually raised the ceilings on those contracts, authorizing more than $3.3 billion to the four companies.65  To off-set the public criticism, FEMA awarded up to $3.6 billion in temporary hurricane-victim housing contracts to small and minority-owned firms.66

In another case, a sole-source printing services contract for $200,000 was awarded without any evidence of competition or justification of urgency.  For one order placed under the contract, the contracting officer did not obtain a price quote for printing 60,000 brochures.  The $34,015 billed for this printing service was paid without evidence of a prior agreement on price.67

While emergency circumstances give the government some leeway in entering into contracts that lack full and open competition,68 FEMA did not consistently re-compete contracts once the emergency period ended.69  For example, while FEMA’s decision to hire the paramilitary security firm Blackwater to provide law enforcement assistance in the area was questionable, the government found the contract terms “appropriate” and the contract price ($950 per security officer per day) “reasonable.”  However, the changing security requirements from the emergency response period meant that the government could have “reduce[d] costs by soliciting competitive proposals using a mix of armed and unarmed security personnel.”70 There were many out-of-work local law enforcement officers who have could been employed, and therefore the government could have saved hundreds of dollars per person each day.

Federal agencies use the excuse that because they need to buy goods and services quickly, they cannot wait to solicit competitive bids from prospective vendors.  One example that disproves that myth was the Military Sealift Command’s effort to procure cruise ships to be used as temporary housing for FEMA.  Although the results of this effort have met with ridicule, because the low occupancy rates caused the per person cost to skyrocket, the government did conduct a competition in 19.5 hours and received offers for 13 vessels from seven contractors.71

Lack of Accountability

To ensure that taxpayer dollars are being spent responsibly the government must regularly monitor and audit contracts.

Poor Oversight of Contracts

Poor oversight in the award and monitoring stages of contracting is one of the most recurrent problems in the federal government’s response to Hurricane Katrina.  Adequate staffing was a huge problem for FEMA.  According to one Department of Homeland Security official, FEMA was authorized to hire approximately 60 contracting officers before Hurricane Katrina hit U.S. land72-- some government reports have stated that 172 acquisition officials were needed.73   The agency, however, was severely understaffed – with only 36 contracting officers on staff.74   Director Paulison has stated that FEMA is now getting the resources it needs and that he is working with Congress to increase the size of the agency.75  

In addition to the lack of personnel was the lack of institutional memory. Many government reports attributed the lack of oversight to the frequent rotation of officials in and out of the areas, and other acquisition officials being “borrowed” from other agencies.  All too often, there was no overlap in the rotation, allowing valuable institutional memory and scenario-specific information to be lost.76

As a result of inadequate contracting staff, mistakes were multiplied, some of which have been detected by post-award audits. Members of the House Government Reform Committee found that mileage claims were overstated and duplicate bills were submitted for debris removal and other services.77  Additional examples of problems includes the arrest of  two temporary FEMA employees for soliciting a $20,000 bribe in return for inflating a catering contract.78  One of the most costly mistakes was an alleged computation error missed by FEMA officials that would have resulted in Bechtel double-billing the federal government $48 million, if it had not been found by the Defense Contract Audit Agency.79  These mistakes were only caught because of the tremendous emphasis on after-the-fact review. They might never have been made had the necessary oversight of government contracts been in place during the duration of the contract.80

Poor contract oversight is exacerbated by the lack of communication among agencies that delegated acquisition functions.  For instance, FEMA tasked GSA to write three contracts in Louisiana for base camps, hotel rooms, and ambulances, worth over $120 million. GSA contracting officers awarded the contracts, but FEMA did not perform its oversight mission and the FEMA officials listed as the points of contact had no knowledge of the contracts.  The GAO reported that “only after contacting multiple FEMA officials over a 3-week period were we able to determine the agency officials responsible for contract oversight.” 81

In another case, the government overpaid Clearbrook $3 million because of a mathematical error.82 That contract was riddled with other problems, as well, including the payment of $4.9 million prior to the effective date of the contract, billing the government as if the government were a “time and material plus fixed per diem rate contract” rather than the contract’s fixed price provision, 83 the absence of details about the scope of work to be done, and a lack of documentation supporting price reasonableness.84

In some cases, oversight suffered due to inadequate documentation necessary to track government spending.  For example, the Department of Transportation Inspector General (DOT IG) reviewed the Federal Aviation Administration (FAA) contract with Landstar Express America for the transportation of commodities such as water, ice, and food.  The IG found that “better internal controls over the emergency disaster relief transportation services contract are needed to ensure that the Government receives the transportation services it pays for….The contracting officers were relying on documentation provided by the contractor to verify that transportation services had been provided as billed.”85  In other words, the government relied on contractors to support their own invoices – an example of contractor self-policing. Landstar had submitted 570 invoices for its services.  When the DOT IG arrived to perform audits, only six of them had been paid – but those few invoices alone had resulted in $33 million in overcharges.86   Imagine the magnitude of overpayment likely to have been discovered if all 570 invoices had been paid.

Another example of inadequate oversight involves FEMA’s transportation support services contracts, which lacked performance standards. As a result, those services were “unresponsive and unreliable” – complaints with transportation services ranged from drivers being slow to make deliveries, drivers who were quick to turn back due to poor road or weather conditions (even in instances when the roads were open), and in one instance, “a driver claimed to be en route but a tracking device indicated he was still in a parking lot where he was found asleep.” 87

The “blue roof” program is another example in which poor contract oversight resulted in wasted taxpayer dollars.  FEMA and ACE entered into contracts to cover wind-damaged roofs with blue tarps.  The main contractors—the Shaw Group, Simon Roofing, and LJC Construction—subcontracted the work out to contractors who in turn subcontracted the work.  Due to the many levels of subcontractors, the multi-tiered contracts were sometimes inflated as much as 1,700% of the job’s actual cost; the taxpayer paid an average of $2,480 per roof for a job that should cost under $300, overbilling the government by $12.5 million. 88

Vague Contracts with Inadequate Cost Controls

FEMA currently lacks a contracting template that clearly defines the expected roles, responsibilities, deliverables, and performance measures for contractors implementing FEMA’s missions.89  As a result, many of FEMA’s contracts were incomplete and included open-ended or vague terms, which raised contractors’ concerns about liability and changing requirements.90  FEMA also did not use a standard contract specifications template for many of the products and services that it purchased, despite the fact that the same products and services were obtained on a regular basis.91  Ambiguous contractual terms often led to inefficiency and waste.

For instance, an “agreement” with Corporate Lodging Consultants, Inc. (CLC) for emergency lodging for evacuees failed to include any mechanisms to control lodging costs (i.e., incentives or penalties regarding lodging cost goals or a per night cap).92  In fact, the per-night room rate escalated from the task order estimated price of $60 to as high as $364 and, as late as December 2005 FEMA was still paying those relatively high prices because the contract did not clearly outline price expectations.  FEMA also was charged room rates that were considerably higher rates than the hotels’ published rate -- discrepancies that ranged from $44.95 to $114.08.93

One of the most publicized example of inadequate cost controls was seen in FEMA’s portable classroom contract with Akima.  Although the contract price increased nearly $8 million overnight, eventually bringing the final contract price to $39.5 million, 94 federal officials did not appear to question the higher amount or ask for any justification for the “inflated” price.95

Government investigations also found that many large contracts were awarded with pre-award cost authorizations without spending limits.  Even by November 1, 2005, long after the need for urgent action had past, the verbal authorizations and letter contracts with Bechtel, CH2M Hill, Fluor and Shaw Environmental for temporary housing had not been converted to formal task orders with definitive pricing.96

Government Purchase Cards

In response to the immediate need to get goods and services to victims quickly, despite existing authority to do so,97 Congress and the President drastically raised government purchase card limits from $2,500 to $250,000 per purchase.98 The result of that increase was that competition requirements were waived for any purchases up to that extraordinarily-high limit, therefore placing taxpayer dollars at unnecessary risk.99 Government purchase cards have a history of being outrageously abused – with government employees buying escort services and a much-publicized breast implant operation for a Hooters waitress, among others.100  After much public outcry, the White House announced on October 3, 2005, that it was returning the government purchase card limit to $2,500, stating “the higher purchase limits are no longer needed and will be used only in ‘exceptional circumstances’ in order to guard against fraud and abuse.”101

Government purchase cards were intended to be used by government officials to buy everyday items such as cell phones, office supplies, construction equipment, computer products, clothing, sleeping bags, rental cars, lodging, refrigerators, coolers, syringes, and digital cameras.  While a well-controlled purchase card program can reduce transaction processing costs and provide agencies with flexibility to achieve their mission objectives, government purchase cards in response to Hurricane Katrina were used in what GAO has described as a “weak control environment.”102

The GAO detailed “numerous examples of potentially fraudulent, improper, and abusive or questionable transactions,”103 including the purchase of a beer brewing kit for $230, a 63-inch plasma screen television costing $8,000 that was found unused in its original box six months after being purchased, training at a golf and tennis resort for $2,000, iPods for $7,000, dog booties costing $68,000, and expensive shower units that cost $71,000.104

To be effective, the purchase card program requires written authorization; independent documentation that items have been received; reconciling underlying receipts/sales slips to monthly purchase card statements and the identification of any invalid charges to prepare dispute forms; and a follow-up on any dispute forms.105

Unfortunately, the responsible official, the Department of Homeland Security’s Chief Financial Officer, did not make sure that these controls were consistently applied, and many organizational elements failed to follow up with cardholders who did not supply supporting documentation.  The result was that 10,339 transactions between December 2003 and February 2006 were not audited.106

A statistical review of DHS purchase card transactions found that 45 percent of transactions did not have the recommended prior written authorization and approximately 63 percent of transactions lacked evidence that the goods or services were actually received.107

Another problem identified by GAO was the high number of cards that were open, but had not been used.  As of December 2005, approximately 19 percent of purchase cards (2,468) had open accounts that had not been used since January 2005, despite the fact that OMB and GSA have clearly stated that purchase cards should only be issued to individuals who have a documented need to acquire items from the government with the purchase card.108

Additionally, GAO found that approving officials were frequently assigned more cardholders than they could effectively supervise.  In one case, three Coast Guard approving officials managed over four times the number of cardholders that DHS has considered effective.109  In six instances, the cardholder and approving official was the same person, presenting a significant conflict of interest.110

Minimal Transparency

To regain public faith in the contracting system, the government must ensure that the contracting process is open to the public, including pre-award decisions, contract data, and contracting officers’ decisions and justifications. This means the process should be transparent, not only for the public to see which contractors are getting paid taxpayer dollars to provide goods or services, but also for government auditors to be able to access adequate documentation to do their work.

Unlike the contracting situation in Iraq, the government has posted some -- albeit limited -- Katrina and Rita contract information on the web.  Although the federal government has a long way to go to catch up with technology by posting actual contracts and all task and delivery orders online, GSA, the Army Corps of Engineers, and FEMA posted spread sheets that provided insights into government spending.

For example, GSA, the Army Corps, and FEMA have publicly posted limited contract data.111  The information, however, did not include detailed information about the level of competition or specific cost or pricing data.  One highlight was the Army Corps’s posting of links to some of its contracts.112  Although some of those contracts were redacted and line-item costs were not associated with the services being provided, that minimal level of transparency allowed the public to better understand the actions of the government.

Another transparency problem was that many contract files for the response to Hurricane Katrina did not contain any source selection information explaining why contracts were awarded to particular contractors, and often contained little or no documentation about “price reasonableness.”113  In some cases, contracting officers agreed to multi-million dollar price quotes without any documentation.  Other contracts were awarded with limited terms, conditions, scope of work descriptions, and prices.114  In fact, it appears there was no source selection process for some contract awards.115 Simply stated, the contracting system for Hurricanes Katrina and Rita allowed payments to be made first and questions to be asked later, exposing taxpayers to large risks and wasting resources that could have directly aided Hurricane victims.

For more information on government contracts, please visit:
GSA’s lists of Katrina and Rita contracts https://www.fpds.gov/.

Army Corps of Engineers contractshttp://www.hq.usace.army.mil/cepa/katrina/contracts.pdf and http://www.mvn.usace.army.mil/hps/contract_information.htm.

FEMA’s Katrina contractshttp://www.dhs.gov/interweb/assetlibrary/CPO-KatrinaContracts.pdf.


Recommendations

Poor Government Planning

1. Emergency officials should review previous post-event reports to make sure that recommendations are incorporated into future contingency plans, thereby learning from prior successes and failures.

2. All major agencies should conduct reviews to pre-determine the contracts they are likely to require for goods and services during an emergency situation.  These needs are likely to include search and rescue; rapid assessment teams; medical evacuation; sheltering and temporary housing; commodity distribution; and debris removal.

3. Agencies should enter into pre-established contingency contracts with multiple vendors in regions throughout the entire U.S.  Vendors should include small and local contractors in order to jump-start the local economy.

4. The federal government should make better use of existing contracts during emergency response situations, rather than entering into new and potentially risky contracts.  This is not an endorsement of interagency contracting in non-emergency situations.

5. The government should create a centralized database which lists instances of contractor misconduct so that government procurement officials can make informed contracting decisions prior to committing federal funds.  Currently, POGO provides this service on its website, www.pogo.org.

Confusion about the Stafford Act

1. Congress should review pre-declaration activities authorized under the Stafford Act to ensure agencies can adequately respond to an imminent emergency event.

2. Congress should resolve ambiguities in the Stafford Act regarding local contractor preference.  In addition, clear, unambiguous remedies and penalties for failure to meet such statutorily-mandated preferences may need to be considered.

Inadequate Competition

1. Government agencies should conduct full and open competitions, to the maximum extent practicable, for all non-urgent purchases, including contingency contracts that are needed to meet any forthcoming emergency event. Agencies should require multiple competitive bids for task and delivery orders before the contract can be considered “competitive.”

2.  Agencies should only utilize the existing exceptions to full and open competition found in federal regulations and ensure that non-competitive contract pricing is fair and reasonable.

3. Agencies should conduct limited competitions for urgent purchases, whenever possible, but obtain the lowest practical cost and rebid them once the emergency period ends.

Poor Oversight of Contracts

1. All federal agencies should rebuild acquisition and oversight staff to meet their missions and have plans in place to supplement their staff with qualified acquisition professionals in an emergency event.

2. Acquisition staff must ensure that the government is using the most appropriate contracting vehicle when the contract is awarded – entering into fixed-price contracts and avoiding high-risk performance-based or “time and materials” contracts that are prone to abuse.  In the event that these risky contracts are necessary for expediency, they should include measurable performance standards and cost caps.

3. Acquisition staff must perform post-award contract oversight on the need for the goods and services, the level of competition, price/cost fairness and reasonableness determinations, type of contract used, and the duration of the contract.

4. Interagency contracts should be monitored by all parties, including the buying agency, the ordering agency, and the contractor.

5. FEMA should avoid rotating contracting officers.  When “borrowing” is necessary, FEMA should make sure that new contracting officials are de-briefed by the previous official to reduce the loss of institutional memory.

Vague Contracts with Inadequate Cost Controls

1. FEMA should develop a contract mechanism that clearly defines the expected roles, responsibilities, deliverables, and performance measures for contractors.

2. Agencies should adhere to well-defined contract templates to reduce contract ambiguities and omissions.

3. Agencies should guarantee that contractors provide documentation for goods and services prior to payment of invoices.

Government Purchase Cards

1. Congress should pass the “Purchase Card Waste Elimination Act of 2006” (S. 457) which would require additional guidance to improve the management of the government’s purchase card program.

2. The government should consistently implement purchase card program internal controls.

3. Purchase cards should only be issued to individuals who have a documented need to acquire items for the government.

4. Purchase card accounts should be conditional on cardholders receiving training on the program’s key internal controls, which should reduce fraudulent and abusive purchases.

5. No cardholder should be their own authorizing official.

6. Agencies should confirm that approving officials review cardholder support and certify monthly statements.

Minimal Transparency

1. The government should post all contracting opportunities online.

2. Federal agencies awarding contracts, procuring goods or services through existing contracts or agreements, or disbursing grant money should create publicly available websites with copies of all contracts, task/delivery orders, grants, and other disbursements so that Congress and the American public can track the billions of dollars that are being spent.  Congress should pass the “Federal Funding Accountability and Transparency Act of 2006” (S. 2590) to improve public access to federal spending.

3. The government should create a new online database listing all non-competitive contracts and awards.

4. Agencies should enter timely, consistent, and accurate contracting information in the Federal Procurement Data System-Next Generation System (FPDS-NG), available at https://www.fpds.gov/.

5. Agencies need to better document contract files per the regulatory requirements.  The government should not pay a contractor until applicable documentation and invoices are received and verified.




Home I Archives I Expose I Search I Donations I Investigations I About Us I Contact Us I Press Room
Site Map I Web Overseer I Site Policies
---

© The Project On Government Oversight 2006
updated:Friday, September 08, 2006