|
|
POGO Letter to DOE Secretary Samuel Bodman, regarding the plutonium pit production program
January 18, 2008
The Honorable Samuel W. Bodman
Secretary
Hard copy to follow
Dear Secretary Bodman:
We have a growing concern with the plutonium pit production program being conducted by NNSA. POGO has learned that the first U.S. nuclear warhead trigger, or plutonium pit, manufactured in almost 20 years required 72 waivers (7 administrative specification exception releases (SXR), 8 process SXRs, 4 product SXRs, and 53 engineering authorization changes) from manufacturing specifications in its production. While some of the waivers may have been administrative, POGO has learned that at least some of them were not, but were in fact waivers from technical specifications.
W88 pits are not new. When the Rocky Flats Plant closed its doors in 1989, about 400 of these pits had been manufactured there. Although the manufacturing process used to make these pits has changed from being “wrought” at Rocky Flats, to now being “cast” at Los Alamos, the significant deviation from the extensively tested pits raise questions about the program. Any waivers from specs diminish the quality of the manufacturing process. And large numbers of waivers indicate a poor quality process. In terms of manufacturing, the definition of Quality is “conformance to requirements” (Crosby, Quality is Free, 1979). Although it is not unusual for a few waivers, particularly for the first unit delivered, weapons experts tell POGO the number raises serious concerns. Furthermore, according to sources, POGO understands the second pit manufactured at
On July 2, 2007, there was a major celebration at Los Alamos National Laboratory when DOE announced that the new “diamond-stamped” W88 pit was delivered to the Navy for installation in a nuclear warhead, even though it was six years late. (See http://www.nnsa.doe.gov/docs/newsreleases/2007/PR_2007-07-02_NA-07-27.htm) The cost of producing pits at the old Rocky Flats Plant was in the neighborhood of $2 million -$4 million per pit. The cost of producing pits at
The W88 nuclear warhead is deployed by the U.S. Navy on Trident II submarine-launched ballistic missiles. W76 nuclear warheads are also deployed on Trident II submarine-launched ballistic missiles. However, rather than manufacturing new pits for the W76, the DOE has a Life Extension Program (LEP) to replace W76 components that might wear out, increasing the life of those warheads by 30 years. Barry Hannah, Chairman of the Reliable Replacement Warhead Project Officers Group, said, “the W76 LEP that is currently underway is an excellent program in terms of technology, schedule, and cost. I believe it meets the Navy's need." So why, given the adequacy of the LEP program, are we struggling -- at great expense -- to remanufacture new W88 pits? Furthermore, because the
The problems producing the W88 pit underscore Congress’ skepticism regarding DOE’s preference for more expensive and riskier programs to build new weapons and components over proven programs that extend the life of nuclear warheads. So far, Congress has seen through DOE’s efforts to get expanded capacity to produce new plutonium pits. Since FY2006, Congress has zeroed out funding requests to build a new Modern Pit Facility (MPF), which would have produced up to125 pits per year in a single shift operation. Congress has also rejected DOE’s Reliable Replacement Warhead (RRW) program, which is also predicated on the same logic that the nuclear weapons complex needs to manufacture a new generation of warheads. POGO remains concerned, however, because Sen. Pete Domenici has threatened that the RRW program will re-emerge “sooner rather than later,” despite the fact that the Life Extension Program allows for existing warheads to remain in the stockpile.
If we are having trouble making a few new pits for an old existing, tested system like the W88, why would we buy a pie-in-the-sky promise that DOE can credibly and competently manufacture RRWs? It is illogical to be giving up on the current stockpile whose pits are projected to last for over 100 years. The RRW series as planned does not have a nuclear test pedigree that even approaches the extensive test pedigree of the existing stockpile. The
Given the performance of the W88 pit remanufacturing effort, it appears there are fundamental problems with current pit manufacturing efforts. The solution to this dilemma, however, is not the current reckless path: throwing billions of dollars at high-risk programs to provide on-the-job training for the contractor workforce of an agency with a long history of failed program management. The solution is to minimize the possible risk to the stockpile, to the taxpayers, and to international arms control efforts by focusing on Life Extension Programs and continuing to accelerate the dismantlement of excess warheads.
Sincerely,
Danielle Brian
Executive Director
Project On Government Oversight





